08-1067 57th Street Pennbrook to Cliff Avenue

In 2008 KEI made a number of improvements and repairs to 57th street between Cliff Ave and Pennbrook Ave in Sioux Falls.

Project Owner: The City of Sioux Falls

The work includeded:

  • sanitary sewer repairs.
  • removing 72" storm sewer and replacing it with new 84" concrete pipe
  • salvaging and re-using the old street surface to rebuild 57th Street
  • a sub surface street drainage system to improve drainage in the street
  • concrete and electrical repair and updates
  • milling and overlaying a portion of the existing asphalt street
.

 

 

 


2400 N 4th Ave, Sioux Falls, SD 57104  •   Ph:  605.336.7617  •  Fx: 605.336.7747